Bringing oil and gas expertise to windfarm operations

Canyon Offshore completed the Sheringham Shoal windfarm project in 62 days, trenching a total distance of 49.97 kilometers, averaging .805 km trenched per day.

On its first dive, the T-1200 spent more than 30 consecutive hours on the bottom in trenching mode, logging downtime equaling less than 1.74% of the total project duration.